Overview

The mechanical installation greatly affects the operation, safety and appearance of the system.
Information is provided to mechanically install the unit such as cut-out sizes, mounting procedures and
other recommendations for the proper mechanical installation of the unit.
3.2

Mounting Requirements

3.2.1 Mounting Procedures (Installed in a Panel Door)
Figure 3.1 – Panel Mounting of an EXL10/XL10 PRIME Series OCS
Once the panel design has been completed using the criteria and suggestions in the following sections,
use the following steps to panel mount the EXL10/XL10 PRIME OCS.
1. Remove all connectors from the EXL10/XL10 PRIME OCS unit.
2. Make sure the gasket is installed on the EXL10/XL10 PRIME OCS and is free from dust and
debris. Check that the corners of the gasket are secure.
3. Pass the unit through the panel.
4. Insert each of the ten (10) mounting clips into the slots in the EXL10/XL10 PRIME OCS case. One
clip should be installed on each corner. Lightly tighten each screw so the clip is held in place.
5. Tighten the screws on the clips such that the gasket is compressed against the panel.
Recommended torque is 7-10 in-lbs (0.8-1.13 N-m).