3.7 Trial operation

3.7.1 Start-up schedule

Prepare the machine for trial operation with the help of OPERATING
INSTRUCTIONS. The instructions describe the measures that must be taken to
prepare the machine for operation.
This should be completed when the machine is started up and used.
Machine type:
Machine serial number:
Installation date:
Read the installation and user manuals carefully. Then check the following points:
1. Check:
Water and drain connections
That the machine is evenly balanced
Detergent and drying agent
That the filters and level pipe are in place
That the overheating protection device is reset
2. Filling the machine:
Turn on the power switch and any circuit breakers
Close the hood
Fill the machine with water in accordance with the INSTRUCTIONS FOR
USE
Bleed the hood lifting cylinder (option) as per the manual.
3. Start the machine:
Check the direction of rotation of all pumps
NB! If the direction of rotation is wrong, the phase must be inverted on the
lockable power switch.
Empty the machine and refill it
Check the final rinse flow during filling
N.B.: The machine will fill in two minutes and 15 seconds at the correct
flow. (machine with standard equipment). The flow is regulated by the built-
in ball valve.
4. Check the setting of the reference values:
All the reference values have been set to the recommended values on
delivery
Check the temperatures