Installation Checklist - VESDA -E VES-A00-P Product Manual

Table of Contents

Advertisement

VESDA-E VES-A00-P Product Guide
4.5

Installation Checklist

Site Name
Address
Detector Serial Number(s) and Date of Manufacture
Name of Installer
Signature
Date
Perform the following checks listed below to ensure that all the necessary items are completed before handing
over to a commissioning engineer.
Installation Checks
The detector is securely locked onto the mounting bracket (if in use). Refer to Figure 4-22
on page 27 for further information.
The sampling air pipes are firmly connected to the air inlet ports. Ensure that the pipes are
NOT glued.
The power supply wiring has been connected to the detector.
If required, the end of line resistor for the monitored GPI has been connected. Refer to
Section 4.3.11 on page 40 for further information.
The alarm and fault relay output terminals of the detector have been connected to the fire
panel.
The adhesive tape has been removed from the exhaust port. Ensure that the exhaust pipe
(if fitted) is NOT glued.
The protective film has been removed from the display.
The air sampling pipework has been installed and checked as per the site plans.
42
Done (Y/N)