Installation Checklist

Site Name
Address
Detector Serial Number(s) and Date of
Manufacture
Name of Installer
Signature
Date
Perform the following checks listed below to ensure that all the necessary items are completed before handing
over to a commissioning engineer.
Installation Checks
Is the detector securely locked onto the mounting surface?
Are the sampling pipes firmly connected to the air inlet ports? Ensure that
the pipes are NOT glued into the detector.
Is power supply installed in accordance with local electrical codes and the
power wires been connected to the correct terminals inside the detector?
If required, has the GPI end of line resistor (EOL) been connected?
Have the alarm and fault signaling wires been terminated to the correct
terminals on the detector?
Is the air sampling pipework installed and checked as per the site plans?