Step 4 Reinstall the rear panel.
Step 5 Adjust the cabinet position so that the expansion bolt holes are aligned with the
eight holes at the bottom of the cabinet.
Step 6 Secure antiseismic kits to the floor at both the front and rear of the cabinet by
using eight M12 expansion bolts. The positioning is shown in
Figure 3-17 Securing the antiseismic kits to the floor
----End
3.2.3.2 Installing an IP21 Component
Procedure
Step 1 Install leveling feet at the bottom of the IP21 component, with two long feet on
the front and two short feet at the rear.