Step 1 Open the front door and remove the cover from the power distribution subrack.
Step 2 Determine the cabling mode.
●
●
Issue 15 (2022-01-30)
Remove small covers for routing cables.
Figure 3-37 Removing small covers from the bottom of the cabinet
Drill holes into the large cover for routing cables.
a.
Remove all the cable cover for signal cables and small covers from the
bottom.
b.
Remove the two large covers from the top of the cabinet, drill holes into
them, and install them to the positions where the small covers were
originally.