Commissioning the system
1. Turn ON the system ON/OFF switch on the control
unit.
The commissioning assistant starts automatically.
Note
When the appliance is initially started up, the dis-
play is in German.
Fig. 36
2. Make required settings:
"Language"
■
"Date and time"
■
■
"Energy cockpit"
Repeating commissioning
Note
Required only where control unit application is to be
changed.
Tap the following buttons:
1.
Required parameters
Check all parameters in Parameter level 1 and adjust
if required.
Parameter
Parameter group
53:...
General
54:...
General
55:...
General
98:...
General
9C:...
General
0C:...
Boiler
Note
For overview of all parameters: See from page 49
3. Confirm with
.
The "Commissioning" menu reappears.
4. Confirm with
.
5. Confirm with
to adapt key parameters to the
system, e.g. "Gas type".
or
End commissioning with
ated with factory settings.
Note
All parameters can be subsequently updated: See
from page 49.
6. Confirm with
.
7. End commissioning with
Note
If commissioning was unsuccessful, an error mes-
sage appears.
2. "Service"
3. Enter "viservice" password.
4. "Commissioning"
Check the following parameters on Parameter level 2
and set according to requirements:
Display
Connection on plug
Connection on plug
Connection on plug
Viessmann system number
LON subscriber monitoring
Function butterfly valve
Commissioning
. The system is oper-
.
A1
sÖ
sL
A1
gS
41