Using the Fusion GUI
10.4 Pop-Up for Some Commands While Conversion is Enabled
Some commands will cause a pop-up like the one shown in
conversion is enabled. The settings in the GUI which will cause this pop-up include FREQUENCY_SWITCH,
USER_DATA_01 (Compensation), Vout Mode, and Vout Scale Loop. To change these settings to a new value,
click on Stop Power Conversion then Close and continue. The GUI will automatically disable conversion, write
the new value, and enable conversion again.
Figure 10-4. Pop-up When Trying to Change FREQUENCY_SWITCH With Conversion Enabled
26
TPSM8D6C24EVM-2V0 User's Guide
Figure 10-4
Copyright © 2021 Texas Instruments Incorporated
when trying to change them while
SLUUCK6 – DECEMBER 2021
Submit Document Feedback
www.ti.com
Need help?