www.ti.com
4.2.7 Recommended Wire Gauge
Input connection to the VIN and PGND terminal blocks (T1, T2, and T3) – The recommended wire size is
AWG #12, with the total length of wire less than two feet (1-foot input, 1-foot return).
Output load connection to the VOUT_A, VOUT_B, and PGND terminal blocks (T5, T6, T7, and T8) – The
minimum recommended wire size is AWG #10, with the total length of wire less than two feet (1-foot output,
1-foot return). A thicker wire gauge can be required to minimize the voltage drop in the wires.

4.3 List of Test Points, Jumpers, and Connectors

Table 4-1
lists the test point functions.
Test Point
Name
TP1
PVIN
TP2, TP3,
TP4, TP10,
PGND
TP16,
TP22, TP27
TP5
Remote Sense Vout A (+) VOUT_A remote sense + voltage point
TP6
VOUT_A
TP7
CHA_VoutA
TP8
CHB_VoutA
TP9
Remote Sense Vout A (–) VOUT_A remote sense - voltage point
TP11
PGood_A
TP12
VSHARE_A
TP13
VSHARE_B
TP14
PGood_B
TP15
SYNC
TP17
Remote Sense Vout B (+) VOUT_B remote sense + voltage point
TP18
VOUT_B
TP19
CHA_VoutB
TP20
CHB_VoutB
TP21
Remote Sense Vout B (–) VOUT_B remote sense - voltage point
TP23
CNTL
TP24
CLK
TP25
SMBALRT
TP26
DATA
Table 4-2
lists the EVM jumpers.
Jumper
Name
JP1
AVIN_A
JP2
AVIN_B
JP3
EN_A
JP4
EN_B
JP5
VDD5_A
JP6
VDD5_B
JP7
USB to PVIN
JP8
PMBus to AVIN
Table 4-3
lists the options for the EN/UVLO pin selections on JP2 and JP4.
SLUUCK6 – DECEMBER 2021
Submit Document Feedback

Table 4-1. Test Point Functions

Description
PVIN test point
PGND test point
VOUT_A sensing test point
Channel A for VOUT_A small signal loop gain measurements (B/A setup)
Channel B for VOUT_A small signal loop gain measurements (B/A setup)
PGOOD signal of VOUT_A
VSHARE_A measurement point. Sensitive signal
VSHARE_B measurement point. Sensitive signal
PGOOD signal of VOUT_B
External clock input (SYNC IN) or output to synchronize other devices (SYNC OUT)
VOUT_B sensing test point
Channel A for VOUT_A small signal loop gain measurements (B/A setup)
Channel B for VOUT_A small signal loop gain measurements (B/A setup)
CNTL signal on J2 header
CLK signal on J2 header
SMBALERT signal on J2 header
DATA signal on J2 header

Table 4-2. Jumpers

Description
AVIN_A input source selection
AVIN_B input source selection
EN_A pin selections
EN_B pin selections
External VDD5_A connection
External VDD5_B connection
Short to connect PVIN to micro USB connector
Short to connect USB-to-GPIO 3.3V to AVIN
Copyright © 2021 Texas Instruments Incorporated
Test Setup
TPSM8D6C24EVM-2V0 User's Guide
7

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TPSM8D6C24EVM-2V0 and is the answer not in the manual?

Table of Contents