GBC DELTA Operator's Manual page 65

Table of Contents

Advertisement

Operator Manual
16. MACHINE INSTALLATION
A GBC service technician must install the machine, put it into operation, and train the operating
personnel.
16.1 PREPARE BEFORE INSTALLATION
Even floor with minimum bearing capacity 512 lb/ft
Pressure pneumatic circuit: Connection with compressed air 90 psi (0.6 MPa)
16.2 ELECTRICAL INSTALLATION REQUIREMENT
Nominal voltage
Power requirement
Nominal current
Recommended value of protection
16.3 BECKER AIR COMPRESSOR
Connect the Becker Air Compressor to the receptacle inside the machine cabinet.
!
CAUTION
During compressor installation, ensure that the compressor rotates in the direction of the arrow on the
compressor casing. If it does not, a GBC Service technician must change the electric supply phase.
16.4 MACHINE LOCATION
The machine has to be located as follows:
There should be a minimum gap of 16 in. (40 cm) between the stacking table and wall or
other solid object.
There should be a minimum gap of 30 in. (80 cm) between the external surface of the
machine covers on the drive side and other solid objects (other machine, etc.).
16.5 FLOOR REQUIREMENTS
The machine has to stand on a solid and acceptably even floor with the bearing capacity of 512 lb/ft
2
(25 kN/m
)
66
2
(25kN/m
208 to 240 Vac, 60 Hz, 3 Phase plus ground
6.5 kVA
24 A
30 A
Delta Laminator
2
)
© 2004 General Binding Corporation
2