Powering On the SPU Cabinet (48 V)

Powering On the SPU Cabinet (48 V)
After you power on the Guardian Service Processor (GSP) (+5 V HKP), and check whether the GSP detects
the presence of the UGUY and cells, you are ready to power up the SPU cabinet, or, apply the 48 V power to
the system.
If you are using a crossover cable with your laptop, you may want to review SPU cabinet activity for each
partition configured, as the SPU cabinet powers up and boots. You can open windows for the complex and for
each partition. It is recommended that you open at least two windows:
A window showing all activity in the complex. (If you have been following the installation procedure in
this manual, you should already have a window open on your laptop.)
To display activity for the complex:
Step 1. If you have not already done so, open a separate Reflection 1 window and connect to the GSP.
Step 2. From the GSP Main Menu, select the VFP (Virtual Front Panel) command with the s option.
A window showing activity for a single partition.
To display activity for each partition as it powers up:
Step 1. Open a separate Reflection 1 window and connect to the GSP.
Step 2. Select the VFP command and choose the partition you want to view.
You should not see any activity on the screen at this point in the installation process.
NOTE
You cannot open more than one window using a serial display device.
To power on the SPU cabinet:
Step 1. Switch on the power switch at the front of the cabinet.