Table B-1
Factory-Integrated Installation Checklist
PROCEDURE
Verify presence of UGUY and
cells
Power on cabinet (48 V)
Verify system configuration
and set boot parameters
Set automatic system restart
Run JUST software
Boot partitions (refer to
Table 4-1 on page 87)
List partitions to boot
List primary boot path for
each partition
Check boot paths with
customer and revise as
necessary
List logical cell number
List physical cabinet # of
cell
List cell slot # within
cabinet
List boot device adapter
physical location in card
cage (slot, cabinet, I/O Bay,
and I/O chassis)
Install boot device (if
required)
Power down cell for each
partition
Connect boot device cable
for each partition
Power up cell for each
partition
Boot HP-UX for each
partition
Configure remote login (if
required). See Appendix D.
Verify remote link (if required).
See Appendix D.
Appendix B
(Continued)
IN-PROCESS
Installation Checklist
Using the Checklist
(Continued)
COMPLETED
155