Turning On Housekeeping Power and Logging In to the GSP

After connecting the serial display device, you are ready to switch on the AC breakers and login to the
Guardian Service Processor (GSP). Switching on the breakers powers up the Bulk Power Supplies (BPS) at
the front of the SPU cabinet, which in turn provides +5 V housekeeping (HKP). HKP power distributes +5 V
power to the logic that requires it.
Before powering up the GSP and SPU cabinet for the first time:
Step 1. Verify that the AC voltage at the input source is within specifications for each cabinet being
installed.
Step 2. Make sure:
You are wearing an ESD wrist strap.
The AC breakers are in the Off position. See Figure 3-23.
The cabinet power switch at the front of the cabinet is in the Off position.
The AC breakers and cabinet switches on the I/O Expansion Cabinet (if one is present) are in
the Off position.
Step 3. If you have not already done so, power on the serial display device.
The preferred tool is the CE Tool running Reflection 1.
To power up the GSP, set up a communications link, and login to the GSP:
Step 1. Turn on the AC breakers on the Power Distribution Control Assembly (PDCA) (or assemblies, if
there are more than one), at the back of the SPU cabinet.
Power on any other SPU cabinets that were shipped with the system.
On the front and back panel of a Superdome 32 Way, you should see the HKP (Housekeeping) and
the Present lights illuminate.
Chapter 3
Turning On Housekeeping Power and Logging In to the GSP
Preparing Superdome for Booting
59