Installing an AC SPD Fuse
1. Position the rear of the AC SPD fuse directly in front of the SPD rail. Make sure the top of the AC
SPD fuse hooks over the top of the SPD rail.
2. Once the AC SPD fuse is seated correctly in the SPD rail clip, press the front of the AC SPD
fuse to rotate the AC SPD fuse down and into the release tab on the AC SPD fuse.
If seated correctly, the bottom of the SPD rail should be fully inserted in the release tab.
3. Align the wires over each end of the AC SPD fuse.
4. Secure the AC SPD fuse and wires with the bolts.
5. Installing a safety cover. See "Installing a Safety Cover" on page 37.
6. Close the front door. See "Closing a Front Door" on page 22.
Maintenance Manual
Figure 96. Installing an AC SPD Fuse on Rail
FUSE
Figure 97. Installing Fuses on Posts