7.1 Installation Environment Requirements

7.2 Hardware Installation
7.3 Power-On and Power-Off
7.4 Initial Configuration
7.1 Installation Environment Requirements

7.1.1 Space and Airflow Requirements

To allow for servicing and adequate airflow, observe the following space and airflow
requirements:
l
l
l
l
l
Issue 08 (2019-10-30)
7

Installation and Configuration

Install the server in an access-restricted area.
Keep the area in which the server is located clean and tidy.
To facilitate heat dissipation and maintenance, keep a clearance of 800 mm (31.50 in.)
between walls and the front and rear doors of the cabinet.
Do not block the air intake vents. Otherwise, air intaking and heat dissipation will be
affected.
The air conditioning system in the equipment room provides enough wind to ensure
proper heat dissipation of all components.