When all of the installation works are complete, perform the system initialization operation test using the
test menu of the MMT (Monitoring and Maintenance Terminal) display.
A test program for installation of Drive 1, 2 is available on PSC to perform operation test.
Prepare one cartridge (compatible with the installed drives) on which barcode label is attached for the test
program.
SAIT1: SAIT1-500
SAIT2: SAIT2-800
LTO3: LTX400G
LTO4: LTX800G
LTO5: LTX1500G
Upon completion of the operation test, output the System Information data and save it.

7-1. Confirming Operation

1. Turn on all the power supplies of PetaSite main unit.
n
There are two types of the CSM-200 depending on the internal power supply system; one type of the
CSM-200 contains a single power supply while the other type contains the dual power supplies.
Refer to the illustration below to turn on the power supplies correctly.
For the CSM-200 that contains the single power input system
Turn on the switches 1 through 6 shown in the figure.
For the CSM-200 that contains the dual power input systems
Turn on the switches 3 through 6 shown in the figure.
Single power input system
6
3
4
5
CSM-200
Section 7

Operation Check

6
3
4
1
5
ON
OFF
2
ON
OFF
Dual power input systems
7-1