5.4 Powering On the Equipment

Context
Understand the switch names and positions before performing power-on commissioning. For
details, see
Before starting the compressor, ensure that the electric heating belt of the crankcase has been
preheated for more than 12 hours. Otherwise, the compressor will be damaged, and Huawei
shall not be liable for any such consequences.
Procedure
Step 1 Switch on the smart cooling product switch in the upstream PDC.
Step 2 Verify that the QF3 switch that controls the outdoor unit and compressor, QF4 switch that
controls the heater and humidifier, MD1, and MD2 are ON.
Step 3 When the device is powered on for the first time, log in as the Admin user. Then set the
following parameters on the displayed Quick Settings page:
Step 4 Choose Settings > System Settings > T/H Sensor to enter the T/H Sensor screen. You can
configure the T/H control types and set points.
----End

5.5 Commissioning Procedure

Context
Issue 03 (2020-01-10)
Figure
3-41.
Select the language: English or Chinese.
Select the date & time settings: date format, date, time, and time zone.
Select the monitoring mode.
Copyright © Huawei Technologies Co., Ltd.
5 Power-On Commissioning
139