TREATING PROCESS FOR HYDRAULIC LIFT INSTALLATION
1. If the treater is not in the bottom position, go to the Load / Unload screen and press
the Lower Treater button and hold it for two seconds.
2. Lift a box of seed and position the gate over the center of the inlet hopper.
DO NOT open the gate.
3. From the Load / Unload screen, press and hold the Load Treater button for two
seconds.
4. After the mix motor reaches speed, open the gate on the pro box. Once all of the
seed is in the treater, press the load treater Stop button.
5. Lower the empty pro box to the ground and position it in front of the discharge
chute.
6. From the Load / Unload screen and press the Raise Treater button and hold it for
two seconds.
7. After the treater is in the top position, move the empty pro box under the discharge
chute.
8. From the Pump screen, press the Liquid Selection button and follow the popup
screens to select the chemical you wish treat the seed with.
9. From the Main screen, press the Start Setup button. Review the settings from
the Blend Setup screen. If any parameters need to be changed, press the Adjust
Settings button and make the changes. If you are not using any auxiliary pump
stands, set the time for Auxiliary 1 Run Time: and Auxiliary 2 Run Time: to zero.
Return to the previous screen, press and hold the Start Blend button for two
seconds.
10. After the batch run is complete, return to the Load / Unload screen. Press and hold
the Unload Treater button for two seconds and let the system run until all of the
seed is discharged to the empty pro box. Then press the unload treater Stop
button.
11. Remove the full pro box from under the treater and press the Lower Treater button,
hold it for two seconds. When it is in the bottom position you are ready to repeat