6. Positioning the treater with hydraulic legs:
When the U-Batch™ Treater is ordered with the hydraulic lift option the treater and the
legs are shipped already assembled.
Lower the machine and place it in the final working position. Make sure there is ample
room for a forklift to remove full pro boxes and replace them with empty ones as well
as lift a pro box over the inlet hopper.
Do NOT anchor the U-Batch™ Treater to the floor until all
NOTICE
connections for the lifting mechanism have been established and the
treater is raised to the maximum height to verify ceiling clearance.
Place the hydraulic power supply in the desired location. The hydraulic fluid reservoir
has been filled at the factory for testing. Place the unattached end of the hose track
on the floor so that the ends are aligned (top). Attach the two hoses from the main
assembly to the two hoses from the power supply (bottom).
After power is connected to the control panel, plug in the hydraulic motor power cable
(see page 18, step 15) and the Raise / Lower control cable (see page 17, step 12)
to the control panel. Raise and lower the treater to verify ceiling clearance.
Anchor the treater, hydraulic assembly and the hose track to the floor to prevent the
machine from moving during operation.