Testing The Valves - Festo CPV-VI Series Manual

Valve terminal
Table of Contents

Advertisement

4. Commissioning
4.2

Testing the valves

4-4
Please note
Before commissioning the CPV valve terminal, note the
specifications concerning the medium, see section 3.3.1
"Auxiliary pilot air" in the chapter "Installation".
The CPV valve terminal should be commissioned as follows:
Commissioning variants
Preliminary test of the pneu-
matic tubing
Complete commissioning of the
complete system
Commissioning of the pneumatic components by means of
the manual override is described below. Commissioning of
the CP system is described in the appropriate manual for the
CP node.
Actiivity
Testing the valve-cylinder-com-
bination by means of the manual
override
Installing and connecting the
complete system Program con-
trol via PLC/industrial PC
Festo P.BE-CPV-EN en 0005e