Commissioning
4.2

Testing the valves and the valve/actuator combination

The valve terminal can be commissioned as follows:
Commissioning variants
Preliminary test of the pneumatic tubing
connection
Complete commissioning of the complete
system
Tab. 4.2 Commissioning variants
Commissioning the pneumatic components by means of the manual override is described below.
Warning
Before testing the valve-actuator combination:
– Make sure that nobody is in the danger zone.
Before actuating the manual overrides (MO):
Uncontrolled actuation of solenoid coils can cause the actuators to perform sudden
unexpected movements, which may cause personal injury and material damage.
• Disconnect the operating voltage supply for the solenoid coils from the correspond­
ing connections on the valve terminal.
This prevents accidental actuation of the solenoid coils.
Note
A valve that has been switched by an electric signal cannot be reset by the manual over­
ride. The electric signal is dominant in this case.
• Reset the electric signal before actuating the manual override.
Proceed as follows:
1. Switch on the compressed air supply.
2. Check the functionality and method of operation of each valve-actuator combination by actuating
the relevant manual override (è Tab. 4.3).
Festo – MPAC-VI-EN – 2017-12a – English
Activity
Checking the valve-actuator combination
by means of the manual override (MO)
Installing and connecting the overall system.
Program control via PLC/industrial PC.