2. Commissioning
2.1 Preparing the CPV system for commissioning

2.1.1 Creating the configuration list

Configuration
list
CP-DN8 9806NH
PLEASE NOTE
The CPV valve terminal must be supplied separately
with load voltage.
The field bus interface of the CPV valve terminal is
supplied with voltage via the field bus cable.
Before commissioning or programming you must create
a configuration list of all the connected field bus slaves.
On the basis of this list, you can:
• carry out a comparison between the NOMINAL and
ACTUAL configurations in order to recognize any
connection faults
• access these specifications during the syntax check
of a program in order to avoid addressing errors.
2-3