Connection on the postage meter
Power connection
Installation and commissioning
Connecting the feeder
Caution! If the feeder was previously in a
cold environment (i.e. below 10 °C / 50 °F):
Wait at least 2 hours after unpacking before
connecting the feeder. The feeder needs this
time to adjust to the environmental conditions.
• Connect the feeder connection cable to the
CAN-BUS interface of the postage meter.
Screw the connector on tightly.
• Plug the power cable into the power con-
nection for the feeder.
• Only then plug the power cable into the
power socket.