10 COMMISSIONING

1)
Conduct start, stop and load performance tests on every genset;
2)
Parallel every genset with busbar, and do breaker close/open tests;
3)
Set every genset (e.g. HGM8151) to Auto Mode;
4)
Set HGM8156 in Manual Mode, and make Mains working well, to test whether mains close/open are
normal; when they are normal, open mains breaker;
5)
Start HGM8156 manually, after busbar goes normal, test whether busbar close/open are normal;
after they are normal, close mains breaker;
6)
Press mains close button, and busbar synchronizes mains; after synchronization mains breaker
closes and starts running in parallel;
7)
Conduct load tests and load transfer tests;
8)
Set HGM8156 controller to Auto Mode, and controller will start/stop automatically based on settings
and conditions.
HGM8156 Genset Parallel (With Mains) Controller
HGM8156 GENSET PARALLEL CONTROLLER USER MANUAL
2019-09-10
Version 1.1
Page 34 of 44

Advertisement

Table of Contents
loading

Table of Contents