Hardware Installation

EIP-2201: 1-Port DIN Rail (Terminal Block) Installation

Use the following procedure to install EIP-2201. See
if the DeviceMaster has DB9 serial connectors.
1. Attach the EIP-2201 1-Port to the DIN rail adapter.
2. Connect the power supply and apply power to the EIP-2201 using the power supply specifications on the
product label and the following information.
Observe proper ESD techniques when connecting and disconnecting the DeviceMaster.
a. If the DIN rail is not connected to earth ground, insert the earth ground wire into the chassis ground
screw terminal.
Note: The chassis ground connection is made only if the
DIN rail is NOT connected to earth ground.
b. Insert the DC positive wire into the + screw terminal
and the DC return wire into the - screw terminal.
Refer to
EIP-2101 and EIP-2201: 1-Port DIN Rail
Power Supply
on Page 74 for detailed power
requirements.
c.
Use a small flat head screw driver to lock the wires
into place.
d. Verify that each wire has been tightened securely.
e. Connect a UL Listed power supply and UL Listed
power cord to a power source to apply power.
Note: Do not connect multiple units until you have changed
the default IP address, see
for Configuration
3. Connect the 10/100 port to the same Ethernet network segment as the host PC using a standard network
cable.
4. Verify that the Status LED has completed the boot cycle and network connection for the EIP-2201 is
functioning using the following table.
The STATUS LED on the device is lit, indicating you have power and it has
completed the boot cycle.
Note: The Status LED flashes while booting and it takes approximately 15 seconds
STATUS
LINK
If the LINK (green) LED is lit, it indicates a working Ethernet connection.
If the ACT (yellow) LED flashes, it indicates network activity.
ACT
Note: For additional LED information, go to the
Do not connect RS-422/485 devices until the IP address is configured and an
appropriate port interface type has been configured. The default port setting is RS-232.
5. Go to
Preparing the DeviceMaster for Configuration
configure the DeviceMaster for use.
12 - Hardware Installation
Preparing the DeviceMaster
on Page 21
EIP-2201 LED Descriptions
for the Bootloader to complete the cycle. When the Bootloader completes the
cycle, the LED has a solid, steady light that blinks approximately every 10
seconds.
DeviceMaster EIP | UP Hardware Installation and Configuration Guide: 2000633 Rev. C
EIP-2101: 1-Port DIN Rail (DB9) Installation
Positive†
5-30VDC
PW1
† Wire gauge: AWG 12-22
Status LED
table on Page 80.
on Page 21 for default network settings and how to
on Page 13
Positive†
Return†
Chassis
5-30VDC
Ground†
PW2

Advertisement

Table of Contents
loading

Table of Contents