Siemens SINUMERIK 840D sl Commissioning Manual page 24

Cnc: shopturn
Hide thumbs Also See for SINUMERIK 840D sl:
Table of Contents

Advertisement

4 Commissioning
4.2
Initial start–up
4-24
ShopTurn on NCU
Via operating area "Services"
directory /CYCLE_STORAGE, load
the definitions and cycles from the
subdirectories:
Load the definitions DEFINES.ARC
from STANDARD CYCLES.
Load the definitions
ST_DEF_E.ARC from
SEQUENCER CYCLES.
Load the definitions DEFINES.ARC
from MEASURING CYCLES.
Activate the files SMAC_SC.DEF,
SMAC_ST.DEF, GUDx.DEF (x = 5, 6,
7) and GUD7x(x=_JS, _MC, _SC,
_ST).DEF by pressing the softkey
"Activate".
Load the cycles CYCLES.ARC from
STANDARD CYCLES.
Load the cycles ST_CYC_E.ARC from
SEQUENCER CYCLES.
Load the cycles M_CYCLES.ARC
from MEASURING CYCLES.
Load the cycles JOG_MEAS.ARC from
MEASURING CYCLES/JOG_MEAS.
Load CYCCUST_ST.ARC from
STANDARD CYCLES.
Fig. 4-4
NCK SINUMERIK 840D sl installation and startup
SINUMERIK 840D sl Commissioning Manual CNC: ShopTurn – 11/2006 Edition
1
PCU 50.3
Load the definitions
ST_DEF.ARC from the PCU
50.3 archive.
Load the files
SMAC_xx.DEF (xx = SC,
ST) and GUD7_xx.DEF (xx
= SC, JS, ST) by pressing
the softkey "Load".
Activate the files
SMAC.DEF and GUDx.DEF
(x = 5, 6, 7) by pressing the
softkey "Activate".
Load the cycles
ST_CYC.ARC from the
PCU 50.3 archive.
Load these cycles by
pressing the softkey "Load".
Note: The cycles are located
in the directories STANDARD
CYCLES and
MANUFACTURER CYCLES.
If necessary adapt the
machine manufacturer cycle
ST_CUST.SPF from the CD;
(see section 11.2 "Machine
manufacturer cycle") and
transfer from the directory
CYCLES/SC/MANU-
FACTURER CYCLES.
Note: After transfer, the
cycle is located in the
directory USER CYCLES.
PCU 50.3: Load
ST_CUST.SPF by pressing
the softkey "Load"
2
© Siemens AG 2006 All Rights Reserved
11/2006