2. Commissioning
2.1.4
CPX terminal configuration with Siemens STEP 7
2−10
The following sections describe the basic configuration steps
with the SIEMENS STEP 7 configuration and programming
software.
Other controller systems may require other settings or a
different procedure.
The configuration examples shown in this chapter are based
on the use of a Siemens SPS SIMATIC S7−300 and the
Siemens STEP 7 version 5.4 configuration and programming
software. Operation of the STEP 7 software is assumed to be
known in the following.
Note
There are different configuration programs available for a
Siemens PLC. Observe the corresponding procedure for
your configuration program.
Caution
Danger of malfunctions, damage or injuries to people
A valve terminal with defective configuration will also be
put into operation. However, only the modules which have
been correctly configured for type and position will be
activated.
Before commissioning, ensure that the connected
elements (e.g. actuators) do not perform any undesired
or uncontrollable movements.
If necessary, disconnect the load power supply and
compressed air supply.
See also section 2.3, Check list for commissioning the
CPX terminal.