The cable shield is to be grounded at both ends. For extremely EMC-prone environments, the GND may be
connected via a separate individually shielded wire pair to improve immunity to interference.
Fiber-optic Cables
!
WARNING
Laser Radiation! Class 1
Do not look directly into the fiber-optic elements!
²
Signals transmitted via optical fibers are unaffected by interference. The fibers guarantee electrical isolation
between the connections. Transmit and receive connections are represented by symbols.
The standard setting of the character idle state for the optical fiber interface is "Light off". If the character idle
state is to be changed, use the operating program DIGSI as described in the SIPROTEC 4 System Description.

Checking the System Connections

3.2.2
!
WARNING
Warning of dangerous voltages
Non-observance of the following measures can result in death, personal injury or substantial prop-
erty damage.
Therefore, only qualified people who are familiar with and adhere to the safety procedures and
²
precautionary measures should perform the inspection steps.
!
CAUTION
Take care when operating the device without a battery on a battery charger.
Non-observance of the following measures can lead to unusually high voltages and consequently,
the destruction of the device.
Do not operate the device on a battery charger without a connected battery. (For limit values see also
²
Technical Data, Section
Before the device is energized for the first time, it should be in the final operating environment for at least 2
hours to equalize the temperature, to minimize humidity and to avoid condensation. Connections are checked
with the device at its final location. The plant must first be switched off and grounded.
Proceed as follows for checking the system connections:
Circuit breakers for the auxiliary power supply and the measuring voltage must be opened.
Check the continuity of all voltage transformer connections against the system and connection diagrams:
Are the voltage transformers grounded properly?
Are the polarities of the voltage transformer connections the same and correct?
Is the phase assignment of the voltage transformers correct?
Is the polarity for the voltage input V
voltage)?
If test switches are used for the secondary testing of the device, their functions must also be checked.
142
4.1 General Device
Data).
correct (if used e.g. for broken delta winding or busbar
3
SIPROTEC 4, 7RW80, Manual
C53000-G1140-C233-4, Edition 07.2018

Advertisement

Table of Contents
loading

This manual is also suitable for:

Siprotec 7rw80

Table of Contents