Figure 2-9
After the monitoring time of the restoration cycle has elapsed, the success of the load restoration will be eval-
uated.
Success basically depends on the following criteria:
•
The load restoration is not blocked, e.g. by another protective function, binary input, undervoltage,
monitoring
•
The monitoring time of restoration cycles of every started load restoration elements has elapsed
•
The maximum number of configured cycles was not exceeded
•
All started load restoration elements are connected
To better illustrate the mode of operation, the following examples demonstrate different scenarios of the load
restoration procedure.
SIPROTEC 4, 7RW80, Manual
C53000-G1140-C233-4, Edition 07.2018
Load Restoration - Blocking and Monitoring
Functions
2.4 Load Restoration