6 Gas
6.1 Gas supply
The following conditions must be met before the gas pipeline is connected
to the unit:
All gas connection parts (also those supplied by the customer) must
●
be tested according to DIN-DVGW (German Association for Gas and
Water).
The central gas supply must not be located within the safety distances
●
and must be freely accessible.
The supply pipeline must have a diameter of at least ¾".
●
WARNING
Risk of fire
Unintended moving of the appliance results in damage to gas line and
possible fire.
→ Do not equip this appliance with casters or with stands with casters.
→ Do not equip this appliance with stands with casters.
CAUTION
Material damage due to insuffient aeration
The amount of fresh air needed for proper combustion is dependent
upon the input power (BTU/hr) of the appliance. In rooms in which the
nominal heat loading caused by all gas appliances is less than 170,721
BTU/hr (50 kW), air supply via external joints or openings into the open
air is permissible.
→ Ensure sufficient supply of combustion air.