Commissioning
Mounting the
terminal box
68
3.2.3 Terminal box and permeate line
One end of the permeate line is already connected with the terminal
box in the factory. The following main steps are necessary for mounting
the unit:
Mounting the terminal box in the vicinity of the analyzer
Connecting the terminal box with the analyzer
Connecting the free end of the permeate line with the control unit.
Note
The terminal box should be mounted in the immediate vicinity of the
analyzer if possible in order to avoid long distances to the permeate
and the dead times associated with it.
1
Open the terminal box.
Fig. 3-7
Mounting the terminal box
2
Screw the terminal box onto a flat wall surface via the four
drilled holes at the corners (Fig. 3-7). Use suitable screws
(max. diameter 5 mm).
3
Close the terminal box.
PurCon IS
Permeate output
ba43133e06
05/2009