The 12-slot UPS weighs 93 kg (204 lb) with the caster cart. Install the cabinet in the rack before
installing power and battery modules and before making connections to the intended power
source.
The Eaton 9PXM UPS and the battery cabinet are very heavy with power modules and battery strings installed.
If installed, before moving the cabinets, remove the power modules and battery strings (see "Power Module
and Battery String Installation" on page 45).
NOTE
NOTE
Use the following mounting procedures to install the UPS cabinet into the equipment rack:
1.
Install rack-mount ears (two per side) on each side of the UPS cabinet (see Figure 10).
Rack-Mount
Ears
Figure 10. Rack-Mount Ear Installed
2.
Select the proper holes in the front vertical rack rails that position the rack tray at the bottom in the rack
and extend the back rails to align with the rear holes. Secure with the screws and washers (see Figure 11).
12
Eaton 9PXM UPS (4-20 kVA) User's Guide P-164000669—Rev 05
The UPS cabinets may be installed in an EIA-standard 48.3 cm (19") equipment rack.
An optional rack-mounting kit (P-157002204), containing brackets and required
hardware, is available.
This procedure is also applicable to the P-103002494 12-slot external battery module
(EBM).