MI 3152(H) EurotestXC (2,5 kV)
Measurement procedure
Enter the R low function.
Set test parameters / limits.
Connect test cable to the instrument.
Compensate the test leads resistance if necessary, see section 7.6.1 Compensation of
test leads resistance.
Disconnect tested installation from mains supply and discharge insulation as required.
Connect test leads, see Figure 7.19.
Start the measurement.
Save results (optional).
Measurement results / sub-results
R
Resistance
R+
Result at positive test polarity
R-
Result at negative test polarity
Figure 7.20: Examples of R low measurement result
100
Tests and measurements