The substructure must be suitable for turning. Also make sure that the floor has sufficient
load bearing capacity and is level.
The substructure must be prepared in a way that possibly used coolant cannot penetrate
into the floor.
Any parts sticking out such as stops, handles, etc. have to be secured by measures taken
by the customer if necessary in order to avoid endangerment of persons.
Provide sufficient space for the staff preparing and operating the machine and transporting
the material.
Also consider that the machine is accessible for setting and maintenance works.
The mains plug and the main switch of the lathe has to be freely accessible.
Provide for sufficient illumination (Minimum value: 300 lux).
In case of little intensity of illumination provide for additional illumination i.e. by a separate
workplace illumination.
INFORMATION
The mains plug of the lathe must be freely accessible.

3.4.2 Load suspension point

Fasten the load suspension gear around the lathe bed.
Make sure that you distribute the loads evenly so that the lathe cannot turn over while lift-
ing.
Make sure that no add-on pieces or varnished parts are damaged due to the load suspen-
sion.

3.4.3 Installation

WARNING!
Danger of crushing and overturning. The lathe must be installed by at least 2 people.
Check the horizontal orientation of the base of the lathe with a spirit level.
Check that the foundation has sufficient floor-load capacity and rigidity.
ATTENTION!
An insufficient rigidity of the substructure leads to superposition of vibrations between
the machine and the substructure (natural frequency of the components).
speeds and moves in the axis with displeasing vibrations are rapidly achieved in case of
insufficient rigidity of the whole system and will lead to bad turning results.
Position the lathe on the intended foundation.
Secure the lathe using the through holes
with the foundation or substructure.

"Dimensions, installation plan TU2506" on page 96

"Dimensions, installation plan TU2506V" on page 97

"Dimensions, installation plan TU2807" on page 98

"Dimensions, installation plan TU2807V" on page 99
GB
TU2506 | TU2506V | TU2807 | TU2807V
Page 104
Original operating instructions
Critical
Assembly
Version 1.0.1
2014-05-16

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Optiturn tu 2807vOptiturn tu 2506vOptiturn tu 2807

Table of Contents