4) Maintenance schedule procedures (maintenance check list)
All stated checks are visual inspections for damage and wear, unless oth-
Inspections
erwise stated.
All listed work must be carried out within the specified period.
Specified period
Checks are carried out as per the maintenance check lists, where type
Maintenance
check lists
and volume of maintenance work is outlined in key words. See chapter
05-20-00 section 5.1).
- The lists must be photocopied and filled out for each maintenance
- The respective check (e.g. 100 hr. check) must be noted on the top of
Extra inspections
- All the maintenance work carried out must be initialled in the "signa-
After maintenance, the completed check lists must be entered in the
Maintenance re-
cords
maintenance records. The maintenance must be confirmed in the log
book.
All discrepancies and remedial action must be recorded in a report of
Discrepancies/re-
medial action
findings to be generated and maintained by the company authorized to
carry out maintenance work. It is the responsibility of the aircraft operator
to store and keep the records.
Replacement of equipment (e.g. governor....) and execution of SB (LTA)
Replacement of
equipment
must be entered in the engine log book, stating
S/N, TSN and date.
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
check.
each page of the maintenance check list.
ture" area by the aircraft mechanic performing the task.
05-20-00
page 9