1) Scheduled maintenance checks
This section lists the periodic inspections which must be carried out after
Definition
a specified period of operation.
Periodic inspections are those which must be performed at 25, 100, 200,
Intervals
600 hr. intervals in accordance with chapt. 05-20-00. section:
This means for example that every 100 hr. of operation a 100 hr. check
must be carried out. Every 200 hr. of operation a 100 hr. and the addi-
tional checks for 200 hr. must be carried out.
100 hr
200 hr
600 hr
- In order to demonstrate continued airworthiness, an engine must be
100 hr.
check
- For the intervals between maintenance work, a tolerance of ±10 hr. is
- If maintenance is performed before the prescribed interval, the next
- If engine has less than 100 hours of operation during one year a
NOTE:
Special hr. check
Effectivity: 912 i Series
Edition 1/Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
25 hr 100 hr 200 hr 300 hr 400 hr 500 hr 600 hr 700 hr to
X
X
X
X
inspected after every 100 hours of operation or 12 months.
permissible, but these tolerances must not be exceeded. This means
that if a 100 hr. check is actually carried out at 110 hr., the next check
will be due at 200 hr. ±10 hr. and not at 210 hr. ±10 hr.
maintenance check is to be done at the same interval (e.g. if first
100 hr. check is done after 87 hours of operation, the next 100 hr.
check must be carried out after 187 hours of operation).
100 hr. check must be carried out. For the annual inspection a toler-
ance of ±2 months is given.
This maintenance schedule contains a column for a 50 hr.
check. This check is recommended by the manufacturer but not
essential, with the exception of oil change when operating with
leaded AVGAS.
Intervals - hours
X
X
X
X
5.1).
2000
hr
X
X
X
X
X
05-20-00
page 3
January 01/2012

Advertisement

Table of Contents
loading

This manual is also suitable for:

912 is

Table of Contents