MECHANICAL INSTALLATION
3 - 4
2.
Press upward on the locking latch, which is located below the handle, and
hold in its raised position. The tip of a small screwdriver may prove helpful in
this operation.
FIGURE 1: Press the latch up and pull the handle
3.
With the latch raised, pull the center of the handle outward. Once disengaged,
continue rotating the handle up to the stop position.
4.
The handle should reach the "stop" position with minimum effort. If the handle
is stuck or hard to rotate to its "stop" position, do NOT force it in order to
withdraw the relay. Re-insert the relay into its draw-out case, and engage the
handle. Arrange to remove the draw-out from the switchgear by removing the
wiring from the terminals. Contact the GE Digital Energy Technical Support
team for any additional assistance.
CHAPTER 3: INSTALLATION
750 FEEDER MANAGEMENT RELAY – INSTRUCTION MANUAL

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

760

Table of Contents