CHAPTER 7: COMMISSIONING
750 FEEDER MANAGEMENT RELAY – INSTRUCTION MANUAL
Transfer Initiated by Undervoltage on Source 1
Energize both test sources at nominal voltage, and wait until the
Transfer Not Ready message is removed from the display of both
Incomer relays.
Turn test Source 1 off.
The Undervoltage 3 feature of the Incomer 1 relay should operate
Output Relay 4 immediately. At Incomer 2, Output Relay 3 operates and
the Transfer Not Ready message is displayed.
When the Undervoltage 4 feature times out, the Incomer 1 relay should
trip Breaker 1 and operate Output Relay 6 to send a Close From Incomer
1 signal to the Bus Tie relay.
Output Relay 6 should reset when Breaker 1 trips, removing the signal
to the Bus Tie relay.
Upon receiving the signal from the Incomer 1, the Bus Tie relay should
close the Bus Tie Breaker.
Check the Event Recorders in the Incomer 1 and Bus Tie relays for the
correct messages and sequences, then clear the recorders.
Manual Restoration of Incomer 1
Turn test Source 1 on and adjust Source 1 to be out-of-synchronism with
Source 2.
At the Bus Tie relay assert Logic Input 6 (Selected To Trip).
At the Incomer 1 relay assert Logic Input 2 (Remote Close).
The Incomer 1 breaker should not close as it cannot pass synchrocheck.
Adjust Source 1 until in-synchronism with Source 2.
At this time the Incomer 1 breaker should close and the Bus Tie breaker
should trip.
Turn off both voltages.
At the Bus Tie relay de-assert Logic Input 6 (Selected To Trip).
Check the Event Recorders in the Incomer 1 and Bus Tie relays for the
correct messages and sequences, then clear the recorders.
Transfer Initiated by Undervoltage on Source 2
Energize both test sources at nominal voltage, and wait until the
Transfer Not Ready message is removed from the display of both
Incomer relays.
Turn test Source 2 off.
The Undervoltage 3 feature of Incomer 2 relay should operate
immediately and operate output relay 4; at the Incomer 1 relay, Output
Relay 3 will operate and the Transfer Not Ready message will be
displayed.
When the Undervoltage 4 feature times-out the Incomer 2 relay should
trip Incomer Breaker 2 and operate Output Relay 6 to send a Close From
Incomer 2 signal to the Bus Tie relay.
Output Relay 6 should reset when Breaker 2 trips, removing the signal
CONTROL SCHEMES
7 - 81