6. The operator should carry out the actions called for in the prepared test sequence. During
calibration, a real-time value is displayed that represents the current magnetic field strength as a
percentage of the maximum limit.
NOTE
It is important that all actions are carried out in the order and at the precise elapsed time
as specified in the prepared test sequence.
7. After completing the prepared test sequence, press the Done softkey. Ensure that a PASSED
message appears on the display. The magnetic deviation value is displayed to indicate the pass or
fail margin of the test. Press the Done softkey to return to the AHRS Page.
190-01115-01 G3X/G3X Touch Installation Manual - GDU 37X Config and Post Install Checkout