14. Start (turn on power) all domains together. Take either of the following two
actions:
Press and hold down (for less than four seconds) the POWER switch on the
■
operator panel.
From a console that is connected to XSCF, execute the poweron -a command
■
of XSCF.
The power to all the domains is turned on, and then the power-on self test (POST)
is executed. When ok prompt displayed on the console of relevant domain, POST
is completed.
For details of the power-on operation, see
on page
4-19, and the SPARC Enterprise M3000/M4000/M5000/M8000/M9000
Servers XSCF User's Guide.
15. Restore the original mode switch setting on the operator panel.
Note – When the maintenance work is completed, be sure to confirm the mode
switch setting and return the switch to Locked.
16. Close the door on the server, and lock it.
Section 4.4.2, "Powering the Server On"
Chapter 23
Switch Backplane Replacement
23-9