The power to all the domains is turned on, and then the power-on self test (POST)
is executed. When ok prompt displayed on the console of relevant domain, POST
is completed.
For details of the power-on operation, see
on page
Servers XSCF User's Guide.
15. Restore the original mode switch setting on the operator panel.
Note – When the maintenance work is completed, be sure to confirm the mode
switch setting and return the switch to Locked.
16. Close the door on the server, and lock it.
22-10
SPARC Enterprise M8000/M9000 Servers Service Manual • June 2010
From a console that is connected to XSCF, execute the poweron -a command
of XSCF.
4-19, and the SPARC Enterprise M3000/M4000/M5000/M8000/M9000
Section 4.4.2, "Powering the Server On"