4. Read the pressure on the manometer and note it
5. Wait a further 15 minutes and note the pressure again after this period.
6. Compare the two pressure values.
The sample gas path is sufficiently tight when the pressure has changed by no more than 4 hPa
(4 mbar) over 15 minutes.
NOTICE
Damage to the analyzer chambers
If you apply a pressure above the maximum value, the bonding of the analyzer chamber
windows could be broken. Discharge of sample gas is possible.
Please observe the pressure data in the section Technical specifications (Page 32).
See also
Replacing the hydrogen sulfide sensor (Page 174)
6.2.2

Gas preparation

Make all gas preparation elements upstream of the analyzer (gas sampling devices, gas cooling
devices, condensation vessels, filters, and any connected controllers, recorders or indicators)
ready for operation. Refer to the associated operating instructions.
6.2.3

Device interfaces

Check that all device interfaces (see Communication (Page 59)) are properly assigned and
configured.
6.3

Commissioning

6.3.1
Commissioning
Once all preparatory work for commissioning has been completed, go through the following
checklist:
• The analyzer is set to the correct operating voltage
• All gas preparation elements are connected and ready for operation, and have been checked
for leaks
• All required connections to and from the analyzer have been established
ULTRAMAT 23
Equipment Manual, 04/2022, A5E37100388-012
Commissioning
6.3 Commissioning
81