JLG 1200SJP Service Maintenance Manual page 272

Hide thumbs Also See for 1200SJP:
Table of Contents

Advertisement

SECTION 4 - BOOM & PLATFORM
41. Apply JLG Threadlocker P/N 0100011 to the bolts and
install the side and upper wear pads into the boom base
section. Torque the bolts to 50 ft.lbs. (68 Nm).
42. Install the boom transport length sensor on the side of
the boom base section.
43. Attach the powertrack tubes.
44. If necessary, attach a source of auxiliary hydraulic power
and retract the boom enough to allow installation of the
cable adjustment plate at the rear of the base boom sec-
tion and install the plate.
45. Install the broken cable sensor and the outer mid extend
cable adjustment nuts.
4-38
46. Install the outer mid retract cable adjustment nuts at the
front of the boom base section.
47. Install the boom length sensors and angle sensors as
tagged during removal.
48. Connect the hydraulic hoses to the telescope cylinder as
tagged during removal.
49. Adjust the boom cables. Refer to Section 4.11 - Wire
Rope Tensioning Adjustment.
50. Perform a boom calibration as described in Section 6
under Calibrating the Boom Sensors.
– JLG Lift –
3121142

Advertisement

Table of Contents
loading

This manual is also suitable for:

1350sjp

Table of Contents