Marking The Rack - Avaya Aura System Platform Installing And Configuring

Table of Contents

Advertisement

Server installation and connectivity
#
5

Marking the rack

6
Attaching rails to the server
page 27
7
Attach the rails to the rack
8
Installing the server in the rack
page 28
9
Replace the cabinet doors, if
necessary
10
Turning on the server
page 28
11
Troubleshoot the installation
Marking the rack
Prerequisites
The rack must be installed. If installing the server in a cabinet, then the doors must be removed.
You must allow 1 U (44 mm, or 1.75 in.) of vertical space for each server you install in the rack.
Rack cabinets that meet EIA-310 standards have an alternating pattern of three holes per rack
unit with center-to- center hole spacing (beginning at the top hole of a 1-U space) of 15.9 mm,
15.9 mm, and 12.7 mm (0.625 in., 0.625 in., and 0.5 in.) for the front and back vertical rails.
Rack cabinets may have round or square holes.
Note:
The vertical rails may be marked by horizontal lines and numbers in 1-U increments. If you
want, you can make a note of the number marking on the rack's vertical rail. It is not
necessary to mark or place tape on the rack
Caution:
If you are installing more than one server, install the mounting rails so that the first server is
installed in the lowest available position in the rack. If you are installing a UPS in the same
rack as the server(s), install the UPS in the lowest available position in the rack and the
servers above it.
1. Place a mark (or tape) on the rack's front vertical rails where you want to locate the
26
Installing and Configuring Avaya Aura
Task
on page 26
on
bottom of the server.
System Platform
on
on
See cabinet manufacturer's
documentation.
Notes