Page 44 of 228
Review Prerequisites Checklist
Preparing for the upgrade
NN43041-465
Standard 01.04
•
Review all product bulletins and Nortel Alerts that impact the site.
•
Prepare a contingency plan for backing out of the upgrade.
DANGER OF ELECTRIC SHOCK
In a DC-powered system, power to the column can
remain on during the following procedures. In an AC-
powered system, however, power to the entire column
must be shut down throughout the procedures.
Preparing for an upgrade involves the following tasks:
•
Identify and become familiar with all procedures.
•
Verify that all installed applications meet the minimum software
requirements for the target platform.
•
Determine and note current patch or Dep lists installed at the source
platform.
•
Determine required patch or Dep lists at the target platform for all
system-patchable components (Call Servers, Voice Gateway Media
Cards, Media Gateway Controllers, Signaling Servers and so on).
•
Determine the required patches or DEP lists installed on all applications.
•
Determine and communicate the required maintenance window,
contingency plan and the impact to the customer to complete the
procedure.
•
Perform an inventory on required software and hardware.
July 2007