Installing Adjustable Base - Zte ZXR10 8900 Series Hardware Installation Manual

Zxr10 8900 series 10 gigabit routing switch
Hide thumbs Also See for ZXR10 8900 Series:
Table of Contents

Advertisement

ZXR10 8900 Series Hardware Installation Manual
24
Confidential and Proprietary Information of ZTE CORPORATION
Note:
To avoid mistakes, measure over and over after all holes line
are marked, and make sure every size is correct.
2. Drilling
Drill φ14 at the expansion bolt hole marked on the floor with
a depth of 90 mm.
Make sure drill is perpendicular to floor when drilling with per-
cussion drill (or hammer). Hold handle tightly and vertically to
avoid sway, otherwise the floor will be damaged and hole will
be enlarged and inclined. If floor is too slip to position drill bit,
cut a dent at the perforation position with punch first to help
locating drill bit.
Use a vacuum cleaner to remove the dust after drilling.
Note:
Marking and drilling are fundamental for hardware installation.
Inaccuracy will impact following operations and affect project
quality.
Operation quality is essential for ensuring whole
project quality.
Result: Adjustable base has been positioned.

Installing Adjustable Base

To install adjustable base, perform the following steps.
1. Install expansion bolts
i. Before installation, clean up dust inside and outside holes
with a vacuum cleaner.
ii. Place base to see if this is aligned with holes.
iii. Remove washer and nut from expansion bolt, and put ex-
pansion bolt and expansion tube into hole. Hammer expan-
sion bolt using a rubber hammer until full expansion tube
of the expansion bolt enters into floor.
2. Adjust base
As shown in
Figure
base, and adjust the flexible frame according to the arrow di-
rection.
16, loose the high locked bolt on adjustable