9-24 Upgrading Your Server
Installation
Install the board to be connected to the PCI board slot depending on the following procedure. Refer
to the manual provided with the board.
1.
Before the installation, set the switches and jumpers on the installed board appropriately
referring to the manual provided with the board, if necessary.
2.
See the section "Preparing for Installation and Removal" described earlier to prepare.
3.
Remove the left side cover.
4.
Press the tabs for the PCI board retention springs one by one to release the lock.
Push each tab to the depth of the server lightly and then push it to the mother board.
A click occurs to release the lock.
5.
Remove the PCI board retention springs from the server.