To install a dual-screen upgrade:
1.
Shut down the system and turn off system power.
2.
Disconnect the cables from the Video and VGA ports on the back of the system base unit.
3.
Open the system base unit as required to gain access to the PCI option board slots. Slots
are identified in "Connecting the Video Cables" later in this chapter.
4.
Use a quarter-inch nutdriver to remove the blanking plates from the following PCI slots:
Z10 board, desktop system: PCI slot 2
Z10 board, deskside system: PCI slot 3
Z10-T board set, deskside system: PCI slots 4 and 5
Retain the screws.
5.
Install the new Z10 board or Z10-T board set in the PCI slots opened in the previous step.
In a dual-screen configuration, the primary and secondary graphics accelerators are
determined as follows:
Z10 boards, desktop system: Primary in slot 1; secondary in slot 2
Z10 boards, deskside system: Primary in slot 2, secondary in slot 3
Z10-T board sets, deskside system: Primary in slots 2 and 3; secondary in slots 4
and 5
6.
Install the screws that were previously removed to secure the Z10 board or Z10-T board
set to the system chassis.
7.
Install the clock sync cable between the Z10 boards or Z10-T board sets, as shown in the
following figures.