2. Extend the server on the standard rails until the server rail-release
latches engage.
Figure 4-17. Extending the server from the rack
WARNING: To reduce the risk of personal injury, be careful when pressing the
server rail-release latches and sliding the component into or out of the rack. The
sliding rails could pinch your fingertips.
3. After performing the installation or maintenance procedure, slide the
server back into the rack:
a. Press the server rail-release latches.
b. Slide the server fully into the rack.
c. Secure the server by tightening the thumbscrews.
Installing the Server 4-21