Equipment Commissioning; Check Before Power On; Power On - Goodwe ETC Series User Manual

Hybrid/ac-coupled inverter 50kw&100kw
Hide thumbs Also See for ETC Series:
Table of Contents

Advertisement

07 Equipment Commissioning

7 Equipment Commissioning

7.1 Check Before Power ON

No.
The inverter is firmly installed at a clean place that is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, battery cable, AC output cable, and communication
2
cable are connected correctly and securely.
3
Cable ties are intact, routed properly and evenly.
The voltage and frequency at the connection point meet the inverter grid
4
connection requirements.
5
The door of the wiring compartment is locked.
6
All the upstream and downstream breakers are disconnected.

7.2 Power On

Step 1 Turn on the AC breaker of the inverter.
Step 2 Turn on the MPPT input breaker of the inverter(Only for ETC series).
Step 3 Turn on the battery breaker of the inverter.
User Manual V1.0-2023-04-30
Check Item
38